value engineering review

In furtherance of the policy set forth in subsection (a) of this section, the Administrator shall require value engineering review in connection with any treatment works, prior to approval of any grant for the erection, building, acquisition, alteration, remodeling, improvement, or extension of such treatment works, in any case in which the cost of such erection, building, acquisition, alteration, remodeling, improvement, or extension is projected to be in excess of $10,000,000. For purposes of this subsection, the term “value engineering review” means a specialized cost control technique which uses a systematic and creative approach to identify and to focus on unnecessarily high cost in a project in order to arrive at a cost saving without sacrificing the reliability or efficiency of the project.

Source

33 USC § 1298(c)